Quiz 7
Question 1
Average productivity for systems of this type = 520 LOC/pm
Burdened labor rate =$6000 per month
a) What is the cost per line of code ?
b) What is the estimated effort in person-months?
c) What is the total estimated project cost?
Question 2
organizational average productivity = 7 FP/pm.
burdened labor rate = $7000 per month
VAF =52
a) What is the estimated number of FPs?
b) Cost per FP ?
c) Estimated effort in person-months?
d) Total estimated project cost ?
Question 3
Based on an average burdened labor rate of $5,500 per month:
a) What is the total estimated project cost?
b) What is the estimated effort in person-months?
Question 4
Using the decision tree below, calculate the expected cost for each option. Use the calculation to make a decision on which is the best option. ( Show all work)
Question 5
How do you change an unrealistic deadline?
Your Answer: